Kitchen Refit in Progress

Kitchen Refit in Progress: Chimney Breast Out and a New Wall

Here is a look at a kitchen we are working on right now. In five days the room has gone from the old kitchen to a new wall, first fix electrics and the new units going in. We will add the finished photos once the job is complete.

The brief

Our client wanted the old kitchen taken out, the chimney breast removed and a brand new Howdens kitchen fitted, all by one team from start to finish. See more of our kitchen work.

What we have done so far

  • Day 1: stripped out the old kitchen
  • Day 2: took out the chimney breast
  • Day 3: built a new stud wall and boarded it
  • Day 4: first fix electrics, with cables chased into the walls and new back boxes set, then the Howdens units started going in
  • Day 5: cored the vent holes through the wall, fitted the vent covers outside and started on the worktops

Coming next

The fit is well under way. Check back soon to see the finished kitchen.